 Presentation Cable Installation CPV16_Somincor revision (⇒ Click here for presentation)

 

4th Quarter of 2015

 - 15 KV Cable installation in suspension mode, at the CPV16 ventilation hole in section 1, at the Neves Corvo mines of Somincor SA.  

(See pictures of work performed - Photos from Somincor Mine - CPV16)

     

    

   

  

 3rd Quarter of 2015

  - 15 KV Cable installation in suspension mode, at the CPV16 ventilation shaft in sections 2 and 3, at the Neves Corvo mines of Somincor SA.                                        

(See pictures of work performed - Photos from Somincor Mine - CPV16)

     

     

    

    

                

 4th Quarter of 2014

 - 24 KV self supporting electrical cables were installed in suspension  mode fixed at one single point, together with one 240mm2 earth conductor and a 24 fiber-optic cable, in one of the main vertical air inlet ducts with about 390 meters depth at the copper and zinc mine of Neves Corvo in Portugal.

  (See pictures of work performed - Photos from Somincor Mine)

     

    

  

  3rd Quarter of 2014

 - Development, manufacture, assembly, installation and comissioning of a new 4000A MCC at the Aljustrel Copper mine in Portugal.

(See pictures of work performed - Photos from Almina Mine)

     

     

     

     

 3rd and 4th Quarter of 2010

1 - Project and execution of alterations of an existing MSB of 4000A from a mineral concentrate production Line at Somincor Mine in Portugal.

2 - Project and building of a new 6300A/100KA MSB.

 (See pictures of work performed - Photos from Somincor Mine)

 2nd Trimestre 2010 

 Off-shore work done in an oil field area for State owned Sonangol. Gestene was responsable for an extensive work of improvements, tests, calibrations ans Tests Reporting of a MV Terasaki Switchboard.

  (See pictures of work performed - Photos from Sonangol)  

 

 2nd Trimestre 2009 

 1 - Maintenance work and alteration improvements on Protection equipment from the MSB and ESB.

2 - Technical assistence oh the Main Generator AVR's and replacement of phase detectors. Final testing with generators on load.

3 - Repairs and technical assistence on the vessels Terasaki automatic monitoring system.Off-shore work done in an oil field area for State owned Sonangol. Gestene was responsable for an extensive work of improvements, tests, calibrations ans Tests Reporting of a MV Terasaki Switchboard.

  (See pictures of work performed - Photos from Vegaland)   

 

 1st Trimester 2008 

 Work done on Reefer Ship in pertnership with an English marine company, having dry docked in 2008 for a complete renovation of the electrical system, introducing a new 725 KVA power pack container, including the power fire detéction and alarm system, navigation system and comunication system, amongst other general required jobs.

 (See pictures of work performed - Photos from Ice Field)   

 

1st Trimester 2007

This project consisted of the replacement and functional improvements in the Power Management System of a Oceonographic Research Vessel, with 4 Generators 600KW each.

 (See pictures of work performed - Photos from MV Gago Coutinho)  

     

 

 

 